This project provided important technical assistance resources to the Marbury VFD to facilitate the evaluation of 22 rural water supply sites, including ponds, in-stream and drafting pool sites. The findings demonstrated that the 11 ponds and impounded water supply points and the six in-stream supply points satisfied the minimum criterion for verification. However, the five drafting pools could not be verified. The project was completed on July 1, 2005.
© Copyright 2007 by Southern Maryland RC&D